Nargesi Gas Gathering, Compression & Injection Project
Nargesi Gas Gathering, Compression & Injection Project
Scope of Work:
– Gathering, compression, and injection of gas from Nargesi Production Unit, capacity of gas
19MMSCFD. The scope was detail engineering, procurement, construction & commissioning ( EPC.)
– Client: National South Oil Fields Co.
– Duration: 30 Months
– Project Progress: completion.
– Major Activities:
– 2 sets of screw compressors+ 8 sets of reciprocating compressors to boost up gas pressure to 3000
psi (injection) .
– Compressor shelter, chemical injection, flares & burn pit, pig launcher / receivers
– Gas dehydration package.
– 8km, 6″ pipeline to injection well( 33MMSCFD).
– 37km over head power line (66kv) & related substations
– Telecommunication and safety systems
– Industrial buildings & facilities
Starting year :
Execution time :
30
Client :
National South Oil Fields Co.
Location :
-
Other projects

Completion of Engineering Services for Units KHT, GOHT, and Isomerization Units of Bandar Abbas Gas Condensate Refinery for Persian Gulf Star Oil Company