Dismantling , Re-installation and Erection of Formalin Complex

Shanul Farayand Consulting Engineers Co.

Dismantling , Re-installation and Erection of Formalin Complex

Dismantling , Re-installation and Erection of Formalin Complex

Dismantling , Re-installation and Erection of Formalin Complex

Scope of Work:
– Engineering, Procurement, Supervising services of 109, 000 TPY Aq. Formaldehyde / 69, 000 TPY Urea Formaldehyde Concentrate (UFC – 80) and 107, 000 TPY Amino (UF) Resin plants
Client: Entekhab Investment Development Group (EIDG)
Technology Provider: Sadepan Chimica Italy
Duration: 24 Months
Project Progress: 60 %
Major Activities:
– Presenting site supervision engineering services (Preliminary and detailed )
– Supervision of dismantling of Formalin plant in Italy
– Supervision, managing and assessment of supervisory reports of main processing equipment and plant
utility
– Re- generation and Preparing engineering documents for construction and erection of plant in Gheshm
– Procurement services
– Managing and Project Control
– Supervision and inspection of subcontractor activities in constructing and erecting and continuous report to client

Starting year :

1

Execution time :

24

Client :

Entekhab Investment Development Group (EIDG)

Location :

Other projects

image-project15

Lavan Gas Wells No.2&3 Facilities & Gas Pipeline

image-project14

Nargesi Gas Gathering, Compression & Injection Project

image-project7

GOHT & KHT Units of Bandar Abbas Gas Condensate Refinery

image-project3

Isomerization Units of Bandar Abbas Gas Condensate Refinery