Scope of Work:
– Detail engineering, procurement services, project control, planning for 3 isomerization units.
Client: Persian Gulf Star Oil Co.
Technology Provider: UOP
Duration: 60 Months
Project Progress: 99.62 %
Major Activities:
– Detail design (process, civil , piping, mechanical, electrical , control, safety, telecom, Hazop, modeling ..)
– Procurement engineering services , Review of Vendor documents.
– Planning & project control.
– Field engineering and Site supports
Project Key Figures :
– Piping(each train): 1850 Lines , 250000 Dia/Inch
– Equipment(each train): 94 , including : 4 compressors,26 pumps,7 columns/reactors, 17 Vessels ,39
Exchanger/Cooler, …
– Steel Structure(each train): 19 No. , 1900 tons excluding piperack
– Civil(each train): 15000 m3 concrete volume
– Electrical /Instrument(each train): 8 MW , 3300 I/O’s (including FF)

Starting year :

Execution time :

60

Client :

Persian Gulf Star Oil Co.

Location :

Bandar Abbas

Other projects

image-project15

Lavan Gas Wells No.2&3 Facilities & Gas Pipeline

image-project14

Nargesi Gas Gathering, Compression & Injection Project

image-project7

GOHT & KHT Units of Bandar Abbas Gas Condensate Refinery

image-project3

Isomerization Units of Bandar Abbas Gas Condensate Refinery